Activity Sequencing
Activity sequencing involves identifying and documenting the logical relationships among schedule activities. Schedule activities can be logically sequenced with proper precedence relationships, as well as leads and lags to support later development of a realistic and achievable project schedule. Sequencing can be performed by using project management software or by using manual techniques. Manual and automated techniques can also be used in combination.
Figure 6-4. Activity Sequencing: Inputs, Tools & Techniques, and Outputs
6.2.1 Activity Sequencing: Inputs
.1 Project Scope Statement
The project scope statement (Section 5.2.3.1) contains the product scope description, which includes product characteristics that often can affect activity sequencing, such as the physical layout of a plant to be constructed or subsystem interfaces on a software project. While these effects are often apparent in the activity list, the product scope description is generally reviewed to ensure accuracy.
.2 Activity List
Described in Section 6.1.3.1.
.3 Activity Attributes
Described in Section 6.1.3.2.
.4 Milestone List
Described in Section 6.1.3.3.
.5 Approved Change Requests
Described in Section 4.4.1.4.
Figure 6-5. Precedence Diagram Method
6.2.2 Activity Sequencing: Tools and Techniques
PDM includes four types of dependencies or precedence relationships:
- Finish-to-Start. The initiation of the successor activity depends upon the completion of the predecessor activity.
- Finish-to-Finish. The completion of the successor activity depends upon the completion of the predecessor activity.
- Start-to-Start. The initiation of the successor activity depends upon the initiation of the predecessor activity.
- Start-to-Finish. The completion of the successor activity depends upon the initiation of the predecessor activity.
Figure 6-6. Arrow Diagram Method
.4 Dependency Determination
Three types of dependencies are used to define the sequence among the activities.
- Mandatory dependencies. The project management team determines which dependencies are mandatory during the process of establishing the sequence of activities. Mandatory dependencies are those that are inherent in the nature of the work being done. Mandatory dependencies often involve physical limitations, such as on a construction project, where it is impossible to erect the superstructure until after the foundation has been built, or on an electronics project, where a prototype must be built before it can be tested. Mandatory dependencies are also sometimes referred to as hard logic.
- Discretionary dependencies. The project management team determines which dependencies are discretionary during the process of establishing the sequence of activities. Discretionary dependencies are fully documented since they can create arbitrary total float values and can limit later scheduling options. Discretionary dependencies are sometimes referred to as preferred logic, preferential logic or soft logic. Discretionary dependencies are usually established based on knowledge of best practices within a particular application area or some unusual aspect of the project where a specific sequence is desired, even though there are other acceptable sequences. Some discretionary dependencies include preferred schedule activity sequences based upon previous experience on a successful project performing the same type of work.
- External dependencies. The project management team identifies external dependencies during the process of establishing the sequence of activities. External dependencies are those that involve a relationship between project activities and non-project activities. For example, the testing schedule activity in a software project can be dependent on delivery of hardware from an external source, or governmental environmental hearings may need to be held before site preparation can begin on a construction project. This input can be based on historical information (Section 4.1.1.4) from previous projects of a similar nature or from seller contracts or proposals (Section 12.4.3.2).
.5 Applying Leads and Lags
The project management team determines the dependencies (Section 6.2.2.4) that may require a lead or a lag to accurately define the logical relationship. The use of leads and lags and their related assumptions are documented.
6.2.3 Activity Sequencing: Outputs
.1 Project Schedule Network Diagrams
Project schedule network diagrams are schematic displays of the project's schedule activities and the logical relationships among them, also referred to as dependencies. Figures 6-5 and 6-6 illustrate two different approaches to drawing a project schedule network diagram. A project schedule network diagram can be produced manually or by using project management software. The project schedule network diagram can include full project details, or have one or more summary activities. A summary narrative accompanies the diagram and describes the basic approach used to sequence the activities. Any unusual activity sequences within the network are fully described within the narrative.
.2 Activity List (Updates)
If approved change requests (Section 4.4.1.4) result from the Activity Sequencing process, then the activity list (Section 6.1.3.1) is updated to include those approved changes.
.3 Activity Attributes (Updates)
The activity attributes (Section 6.1.3.2) are updated to include the defined logical relationships and any associated leads and lags. If approved change requests (Section 4.4.1.4) resulting from the Activity Sequencing process affect the activity list, then the related items in the activity attributes are updated to include those approved changes.
.4 Requested Changes
Preparation of project logical relationships, leads, and lags might reveal instances that can generate a requested change (Section 4.4.3.2) to the activity list or the activity attributes. Examples include where a schedule activity can be divided or otherwise redefined, where dependencies can be refined, or where a lead or lag is adjusted to adequately diagram the correct logical relationships. Requested changes are processed for review and disposition through the Integrated Change Control process (Section 4.6).